Friday, 11 May 2018

UTC_Stephenson Quarter Update



            


                                


16 weeks from completion, works on the UTC at the Stephenson Quarter continue apace.

Masonry verging is complete to the west elevation of the new block allowing the subsequent removal of scaffolding. This signifies a key step towards closing  up the listed building roof and the forming of a link that joins the Hawthorn Engineering Works building to the new build block.

By linking the two slim blocks we create a larger volume at ground level that bridges the two elements and forms the central main hall of the UTC.

Timber repair and conservation works are complete within the listed Hawthorn Engineering works building and the first of the internal scaffold is being removed. Externally, reclaimed slate is now being installed on the reconstructed roof. 

Meanwhile the brickwork to the new block is well underway including the soldier course banding detail.